Fairgrounds bike path project delayed

GOSHEN — The completion of a bicycle/pedestrian trail from U.S. 33 to the Elkhart County 4-H Fairgrounds has been delayed. However, the trail is still expected to be in place for the 2014 fair.

Work by Niles, Mich.-based Selge Construction crews on the Monroe Street trail was originally set to be finished Friday of last week. However, Goshen Board of Public Works and Safety members on Monday approved extending the deadline to April 13 of next year.

The board also approved an addition of $5,264.70 to the project cost, bringing the total contract with Selge Construction to $831,979.43. The new funding is for additional trail construction near the Monroe Street bridge over Rock Run Creek.

Goshen Utilities Engineer Dustin Sailor listed several factors that delayed the project. These included an unforeseen gas line conflict with the storm sewer, delays in the bridge project and winter weather conditions.

Sailor said the bridge replacement project is a separate project by Elkhart County officials, using local funds, and being constructed concurrently with the new trail.

The Monroe Street trail project is being funded with 80 percent federal transportation enhancement funds and 20 percent local funds. When complete, the trail will extend from U.S. 33, running on the north side of Monroe Street (C.R. 34) until it reaches Blackport Drive. The trail will then cross to the south side of Monroe and run all the way to the fairgrounds’ Gate 5.

According to Goshen engineering staff, the overall cost of the Monroe Street trail project — including design, right-of-way acquisition, construction and construction inspection — is in the neighborhood of $1.4 million.

Other business

In other business, the Board of Works approved:

• A bid from D & R Salvage in Goshen for 463 surplus water meters that are no longer needed by the Utility Department. The bid was $569.75 for used Neptune meters and $575 for new Neptune meters.

Text Only
Local News
Parade
Magazine

Click HERE to read all your Parade favorites including Hollywood Wire, Celebrity interviews and photo galleries, Food recipes and cooking tips, Games and lots more.
Poll

Goshen City Council member Dixie Robinson is asking residents to make an effort to clean up their yards this spring. The city’s Dial-A-Truck program is available to haul trash away. Do you think there are more unsightly properties in Goshen this year than five years ago?

Yes, I have noticed more problem properties
No, I have not noticed more problems
I think the problems are about the same as always
     View Results
AP Video
Captain of Sunken SKorean Ferry Arrested Raw: Fire Destroys 3 N.J. Beachfront Homes Raw: Pope Presides Over Good Friday Mass Raw: Space X Launches to Space Station Superheroes Descend on Capitol Mall Man Charged in Kansas City Highway Shootings Obama Awards Navy Football Trophy Anti-semitic Leaflets Posted in Eastern Ukraine Raw: Magnitude-7.2 Earthquake Shakes Mexico City Ceremony at MIT Remembers One of Boston's Finest Raw: Students Hurt in Colo. School Bus Crash Raw: Church Tries for Record With Chalk Jesus Raw: Faithful Celebrate Good Friday Worldwide Deadly Avalanche Sweeps Slopes of Mount Everest Police Arrest Suspect in Highway Shootings Drought Concerns May Hurt Lake Tourism Vermont Goat Meat Gives Refugees Taste of Home Calif. Investigators Re-construct Fatal Bus Cras Mayor Rob Ford Launches Re-election Campaign Appellate Court Hears Okla. Gay Marriage Case